What is this notice about?
Alyeska Pipeline Service Company has asked the Alaska Department of Natural Resources (DNR) to add about 2.63 acres of State land to the Trans-Alaska Pipeline System (TAPS) right-of-way where the pipeline crosses the Middle Fork Koyukuk River at Pipeline Milepost 208. The company wants to build a rock structure in the river to stop erosion near the pipe. People with a direct financial interest who want to keep the right to challenge DNR's decision in court must send written objections by 5:00 p.m. on October 26, 2026.
Why was this notice issued?
Alaska Statute (AS) 38.35.070 requires DNR to give public notice when it receives an application to amend a pipeline right-of-way lease. Alyeska Pipeline Service Company applied to amend the TAPS Right-of-Way Lease, ADL 63574.
What action is being taken?
DNR is reviewing a request to add about 2.63 acres of State land next to the western and eastern edges of the TAPS right-of-way (SE1/4 of the NW1/4 of Section 9, Township 32 North, Range 10 West, Fairbanks Meridian). Over the past decade, changes in the river channel have caused bank erosion upstream of the pipe crossing and worn down the streambed near the pipeline. The company proposes to place a rock grade control structure downstream of the pipe and fill a low spot near the pipe. To let equipment reach the work area, extra rock would be placed to temporarily raise part of the structure near the north bank above the water; that extra fill would be removed when work is done. Equipment would include front-end loaders, a backhoe and trucks. The land would be surveyed and the final area may be smaller than approved for construction.
Who is involved: Alyeska Pipeline Service Company (APSC), applicant; Trans-Alaska Pipeline System (TAPS)
How can the public respond?
Respond by Mon, Oct 26, 2026 This deadline has passed.
“Written objections must be received by 5:00 p.m. on October 26, 2026 (time zone not stated; this is about 60 days after the August 26, 2026 publication).”
Ways to respond
- Mail Department of Natural Resources, Division of Oil and Gas – State Pipeline Coordinator’s Section, 550 West 7th Avenue, Suite 1100, Anchorage, AK 99501
- Email spc.records@alaska.gov
What to include
Objections must be in writing. Under AS 38.35.200, only the applicant, a competing applicant, or a person with a direct financial interest affected by the lease who raises objections within 60 days of the notice can later ask a court to review the commissioner's decision. Court review is limited to failure to follow the required procedures, or an abuse of discretion so capricious, arbitrary or confiscatory that it denies due process. The application is online at http://dog.dnr.alaska.gov/home/newsroom; paper copies are available at cost from DNR. People with disabilities who need help to take part may call (907) 269-8411 TTY/TTD and should give enough advance notice.
Contact
Anthony Strupulis, P.E., State Pipeline Coordinator
Alaska Department of Natural Resources, Division of Oil and Gas – State Pipeline Coordinator’s Section
spc.records@alaska.gov
(907) 269-8800
550 West 7th Avenue, Suite 1100, Anchorage, AK 99501
Will there be public meetings?
The notice does not announce any public meeting or hearing.
Key dates
- Aug 26, 2026: Notice published
- Oct 26, 2026: Deadline (5:00 p.m.) for written objections under AS 38.35.200