SusitnAKAlaska Public Notices, Explained
Active Public comment opportunity Public Notices

Public Notice of Analysis of Proposed Decision TAPS Amendment PLMP 208

What is this notice about?

The Alaska Department of Natural Resources (DNR) has prepared a proposed decision on a request from Alyeska Pipeline Service Company to add about 2.63 acres of state land to the Trans-Alaska Pipeline System right-of-way lease where the pipeline crosses the Middle Fork Koyukuk River, at Pipeline Milepost 208. The extra land would be used to build a rock structure that helps control the river's flow and reduce erosion near the pipeline. The public can send written comments until 5:00 p.m. on December 4, 2026.

Why was this notice issued?

Alaska Statute (AS) 38.35.080 requires public notice. Alyeska Pipeline Service Company asked to amend the Trans-Alaska Pipeline System (TAPS) Right-of-Way (ROW) Lease, ADL 63574. Over the past decade, changes in the river channel have caused bank erosion upstream of the pipeline crossing and scour (wearing away of the riverbed) near the pipeline.

What action is being taken?

DNR has prepared an Analysis and Proposed Decision on adding about 2.63 acres of state land to the TAPS right-of-way lease (case 2026-63574-A3). The land would be used to install a rock grade control sill downstream of the pipe and to fill a depression near the pipe, improving water flow alignment and reducing local scour. A temporary rock platform would be built so equipment such as front-end loaders, a backhoe and trucks can reach the area, and it would be removed when work is done. The land is in the SE1/4 of the NW1/4 of Section 9, Township 32 North, Range 10 West, Fairbanks Meridian, and would be surveyed, so the final acreage may be smaller. If comments show a need for significant changes, DNR will give more public notice; if not, the proposed decision, with any minor changes, will become the final decision after December 4, 2026, without further notice.

Who is involved: Alyeska Pipeline Service Company (APSC), operator of the Trans-Alaska Pipeline System

How can the public respond?

Respond by Fri, Dec 4, 2026 26 days from today.

“Before 5:00 p.m. on December 4, 2026”

Ways to respond

  • Mail Department of Natural Resources, Division of Oil and Gas – State Pipeline Coordinator’s Section, 550 West 7th Avenue, Suite 1100, Anchorage, AK 99501
  • Email spc.records@alaska.gov

What to include

Comments must be in writing. The Analysis and Proposed Decision is available online at http://dog.dnr.alaska.gov/home/newsroom, and hard copies can be bought at cost from DNR at the address above. The case number is 2026-63574-A3 (ADL 63574). People with disabilities who need aids or special help to take part can call (907) 269-8411 TTY/TTD and should give DNR enough advance notice.

Contact

Alaska Department of Natural Resources, Division of Oil and Gas – State Pipeline Coordinator’s Section
spc.records@alaska.gov
(907) 269-8800
550 West 7th Avenue, Suite 1100, Anchorage, AK 99501

Will there be public meetings?

The notice does not announce any public meeting or hearing.

Key dates

  • Nov 4, 2026: Notice published
  • Dec 4, 2026: Written comments due before 5:00 p.m.

Original notice text

NOTICE OF ANALYSIS AND PROPOSED DECISION Trans-Alaska Pipeline System, ADL 63574 Middle Fork Koyukuk River Scour Protection Pipeline Milepost 208 (2026-63574-A3) The Alaska Department of Natural Resources (DNR), pursuant to Alaska Statute (AS) 38.35.080, hereby gives notice that DNR has prepared an Analysis and Proposed Decision for an amendment request submitted by Alyeska Pipeline Service Company (APSC) to add additional lands to the Trans-Alaska Pipeline System (TAPS) Right-of-Way (ROW) Lease, ADL 63574, at TAPS crossing of the Middle Fork Koyukuk River to facilitate the installation of grade control sill. APSC requests to add approximately 2.63 acres of state land to install a grade control sill to provide better flow alignment and reduce local scour. In the past decade there has been continuing bank erosion upstream of the pipe crossing at Pipeline Milepost (PLMP) 208 due to channel changes. The changes in flow pattern resulted in flow concentration on the north bank and local stream degradation in the vicinity of the Pipeline within the active floodplain. APSC proposes installing an initial grade control rock structure downstream of the pipe and fill in a depression in the pipe vicinity. In order for equipment to reach and place rock in the area of interest, the grade control structure near the north bank will be temporarily raised above water level by placing additional rock. Once completed the additional fill material used to build the platform will be removed. Equipment used would include front-end loaders, backhoe, and trucks. The requested amendment area is located on land adjacent to the westerly and easterly TAPS ROW boundary within: the SE1/4 of the NW1/4 of Section 9, Township 32 North, Range 10 West, Fairbanks Meridian, containing a total of approximately 2.63 acres. The requested land would be surveyed and may include less acreage than approved for construction. The public is invited to comment on the Analysis and Proposed Decision. Comments must be submitted in writing to the address below before 5:00 p.m. on December 4, 2026. If public comment indicates the need for significant changes in the proposed decision, then additional public notice will be given on or after December 4, 2026. If no significant changes are required, then the proposed decision, including any minor changes, will be issued without further notice as the final decision after December 4, 2026. Department of Natural Resources Division of Oil and Gas – State Pipeline Coordinator’s Section 550 West 7th Avenue, Suite 1100 Anchorage, AK 99501 Phone: (907) 269-8800 Email: spc.records@alaska.gov The Analysis and Proposed Decision is available online at: http://dog.dnr.alaska.gov/home/newsroom. The public may obtain hard copies of the documents, at cost, from the DNR at the address above. DNR complies with Title II of the Americans with Disabilities Act of 1990. Individuals with disabilities who may need auxiliary aids, services, or special modifications to participate in this review may call (907) 269-8411 TTY/TTD. Please provide sufficient notice for DNR to accommodate your needs. DNR reserves the right to waive technical defects in this publication.

This summary was written by an AI model (Claude) from the official notice text. This is general information, not legal advice. Always confirm deadlines and instructions in the official notice. Legal disclaimer.